Environment ministry sets higher passing score for data centers in Seoul area

Data centers locating in the Seoul metropolitan area will need 75 points to clear the new grid-impact assessment, part of a push to spread large power demand outside the capital region.

By New Era Daily AIAI-writtenPublished
Illustration: Environment ministry sets higher passing score for data centers in Seoul area
Climate, energy and environment — Illustration: New Era Korea Daily · AI-generated

South Korea's environment ministry said Sunday it will begin enforcing a new regulation on grid-impact assessments from Nov. 16, introducing a higher passing score for data centers that locate in the Seoul metropolitan area in an effort to disperse large power demand.

Under the new rule, data centers built in the capital region must score 75 points to pass, up from 70, and a density-of-electricity-use category is added that disadvantages projects in areas where power demand is already heavy.

The regulation formalizes a system that has run as a pilot for two years since the Special Act on the Activation of Distributed Energy took effect in June 2024.

The concentration reflects a sharp regional gap in power self-sufficiency. Seoul meets 12 percent of its electricity needs from local generation and Gyeonggi Province 62 percent, while South Jeolla Province reaches 213 percent and North Gyeongsang Province 216 percent.

Demand from data centers is expected to grow rapidly. The Korea Energy Economics Institute projects that domestic data center power consumption will rise from 5 terawatt-hours in 2024 to 31.6 terawatt-hours in 2040, more than sixfold. Korea Electric Power Corp. has received applications for 178 data center connections totaling 10,068 megawatts, about four times the 2,669 megawatts currently under contract.

The ministry also set rules to prevent speculative applications. Assessment result notices cannot be transferred or sold, and they will be valid for one year in principle, with one extension of up to a year allowed. Applicants who submitted assessment documents before the regulation takes effect but have not received a result notice will be judged under the new standards.

The ministry plans to issue a detailed manual by the end of this year setting out processing procedures and judgment criteria for each category, and to build a comprehensive information support system in early 2027 that lets operators track their applications from document submission onward.

"The regulation strengthens the assessment of grid impact and expands preferential treatment for projects locating in areas with abundant electricity, which will greatly help balanced national development and the stable operation of the power grid," Lee Jae-sik, director general for power grid policy at the Ministry of Climate, Energy and Environment, said in the statement. He added that the ministry will run the expert review system and procedures quickly and transparently so the system takes hold in the field.

What this article is based on

Every fact in this article can be checked against the primary documents below.

  1. Government기후에너지환경부 환경 보도자료· Ministry of Climate, Energy and Environment· accessed Nov. 15, 2026
  2. Other고시 제정안 행정예고 일자· thecodit.com· accessed Nov. 15, 2026
  3. Other소관 부처·제도 도입 배경· dataeconomy.co.kr· accessed Nov. 15, 2026
  4. Government전력계통영향평가 도입 취지·법적 근거· motir.go.kr· accessed Nov. 15, 2026