Data centers outside Seoul area to skip grid impact review under 50MW
The environment ministry and the science ministry plan to exempt smaller AI data centers outside the capital region from grid impact assessments and speed evaluations for larger projects.

The environment ministry said Friday it will exempt AI data centers outside the Seoul metropolitan area with contracted power capacity of up to 50 megawatts from mandatory grid impact assessments, part of a push to speed construction of the power-hungry facilities.
The exemption is being written into the enforcement decree of the Special Act on Promotion of the Artificial Intelligence Data Center Industry, which the government announced for public comment the same day. The law is scheduled to take effect on March 10, 2027.
Under the special act, new, expanded or converted AI data centers in non-metropolitan areas below a power threshold set by decree are already eligible for the waiver. The government settled on 50 megawatts after weighing industry requests against the strain large data centers place on local power grids. Officials concluded that even a 100-megawatt threshold would leave most of the gigawatt-scale AI data centers planned under the government's megaproject program still subject to review.
The environment ministry is also moving to simplify the assessment itself. Under a planned revision to its operating rules for grid impact evaluations, AI data centers inside designated special zones will be exempted from the non-technical portion of the review regardless of size and will undergo only the technical assessment. Officials said operators had been spending much of their preparation time on the non-technical requirements. Separately, the ministry will give priority treatment to AI data centers tied to the megaproject program and to those applying for bundled permitting, again regardless of scale. The priority rules will be written into the assessment manual.
"We have prepared tailored improvement measures through close consultation with the environment ministry so that AI data centers can be built on schedule," said Ryu Je-myung, the science ministry's second vice minister.
His counterpart at the environment ministry, Lee Ho-hyun, said the ministry would keep the grid stable while supporting rapid construction. "We will promptly finish the revision of the notice and the detailed work manual," he said.
What this article is based on
Every fact in this article can be checked against the primary documents below.
- Government기후에너지환경부 환경 보도자료· Ministry of Climate, Energy and Environment· accessed Nov. 21, 2026
- Government기후부 발언· accessed Nov. 21, 2026
© New Era Korea Daily. All rights reserved.