Korea industry ministry reviews Czech nuclear project after builder talks collapse
The industry ministry convened a meeting of all state-run Team Korea companies to confirm schedules for the Dukovany nuclear project and plan the selection of a new construction contractor by July 2027.

South Korea's industry ministry said Thursday it convened a meeting of all state-run companies involved in the Czech Dukovany nuclear project to check progress toward the April 2027 construction permit application and a November 2029 groundbreaking, after negotiations with the original construction consortium ended in October.
Trade, Industry and Energy Minister Kim Jung-kwan chaired the review at the Seoul government complex, the ministry said. The meeting brought together Korea Hydro & Nuclear Power, KEPCO Engineering & Construction, KEPCO Nuclear Fuel and KEPCO KPS.
The session was part of an emergency management system the ministry has run since November, in which the minister and vice minister personally oversee the project. It followed a vice-ministerial review of Korea Hydro's plans on Nov. 2, the ministry said.
The Oct. 29 end of construction contract negotiations with a consortium of Daewoo Engineering & Construction and Doosan Enerbility left Korea Hydro & Nuclear Power, the state utility, with work that must be reassigned. The company told the meeting it had identified the follow-up tasks required and divided them into planning for the contractor transition, a selection plan for a new builder and a schedule for hitting major milestones.
The transition planning covers design and licensing, verification of site information and arrangements for accommodation sites. Korea Hydro said it sorted the work into tasks it can carry out itself, work that can be assigned to Czech companies it has already contracted, and work that requires new contracts, with weekly plans for each to keep the project moving.
The utility aims to complete the selection of a new construction company by July 2027, a shorter period than a standard open competitive tender would take. It will apply the comprehensive evaluation bidding system under the country's state contract law to ensure construction capability, transparency and fairness, the ministry said. Korea Hydro and KEPCO Engineering & Construction will form a dedicated joint task force, draw on bidding materials from the Shinhanul No. 3 and 4 units built in 2023, and hold a briefing session to explain participation conditions in detail.
"We are pushing the related procedures with the goal of selecting a new construction company in July 2027," Korea Hydro President Kim Hoe-cheon said. "Until that selection, we will add company personnel to carry out some of the work directly, and we will manage urgent tasks such as the design of auxiliary facilities through separate contracts so that the necessary work does not stop."
KEPCO Engineering & Construction President Kim Tae-kyun told the meeting that his company, as the dedicated design organization for Dukovany, had submitted about 3,800 design documents on schedule in the 15 months since work began in December 2025 and had signed a first design contract with a Czech engineering firm, with further contracts under discussion.
KEPCO Nuclear Fuel President Chung Chang-jin said his company was carrying out its fuel-related work on schedule and had sent specialists to deliver technology transfer training to the client in May and June. KEPCO KPS President Kim Hong-yeon said the company was responding to Czech requests, including submitting technical materials for construction licensing approval.
Minister Kim said the government would use its ministerial-level consultative body with the Czech government, frequent meetings and weekly director-level talks to maintain confidence in the project and to pass on requests from the Korean side. "The government will strengthen its management role so that the nuclear power companies take greater responsibility and leadership," he said.
What this article is based on
Every fact in this article can be checked against the primary documents below.
- Government산업통상자원부 산업 보도자료· Ministry of Trade, Industry and Energy· accessed Nov. 14, 2026
- Government회의 개최 사실·주재자· motir.go.kr· accessed Nov. 14, 2026
© New Era Korea Daily. All rights reserved.