Government legislation ministry allows three-year solar delay in farm zones
Local governments may enact ordinances to postpone rooftop solar installations on agricultural buildings for up to three years after completion approval.

The Ministry of Legislation said that local authorities can restrict the installation of solar power facilities on building roofs in agricultural promotion zones for three years following construction approval. The ruling clarifies that such time-based limitations fall within the scope of matters municipalities may define through urban and county planning ordinances.
The decision addresses a query on whether a three-year moratorium constitutes a valid condition under the Enforcement Decree of the Act on the Planning and Utilization of Land. The ministry concluded the restriction period qualifies as a concrete matter alongside physical requirements like separation distances, height limits and layout configurations.
Officials determined the provision listing physical criteria serves as an open delegation rather than a closed list, granting local governments broad discretion to establish standards suited to regional conditions. This interpretation aligns with the 2017 amendment to the decree, which aimed to expand local legislative autonomy and strengthen decentralization. Critics had argued that a time limit differs fundamentally from physical conditions and exceeds the authority granted to local ordinances, but the ministry rejected this view, noting that limiting ordinance powers to physical metrics would contradict the law's intent to allow comprehensive regional planning.
The ministry noted that delaying solar installation ensures buildings are initially used for their primary purpose of agricultural production or farmland improvement. Such a pause also supports public interests by promoting harmony with the surrounding landscape and ensuring sound use of farmland. The Legal Affairs Ministry issued this binding interpretation on July 8 in response to a civil petition regarding the specific scope of developable action permit standards.
What this article is based on
Every fact in this article can be checked against the primary documents below.
- Court ruling법제처 법령해석례· Ministry of Government Legislation· accessed Sept. 16, 2026
- Government법제처 주요 기능· moleg.go.kr· accessed Sept. 16, 2026
- Government농업진흥구역 지붕 태양광 설치제한· opinion.lawmaking.go.kr· accessed Sept. 16, 2026